End-of-Year and Annual Student Data Rollover (ASDR)

Annual Student Data Rollover (ASDR) is a process that closes out the current school year and prepares student records for the next school year. This process occurs once a year prior to the start of school and is performed for the entire district.

  • Student grade levels are increased by one. Note that there is an exception for record status 5 students (not currently enrolled in this district, will attend next year): the program considers the grade level to be the next year grade level, rather than the promotion/retention year-end-status codes. ASDR will not promote record status 5 students to the next grade level.

  • Students who are moving to a higher-level school (e.g., from elementary to middle school) are enrolled at the new campus.

  • ASDR moves the student schedules from Scheduling to Grade Reporting for the upcoming school year. Course requests that are not in Assigned status will be dropped from Scheduling.


Before and after running the program, there are a number of steps required as part of the ASDR process, which are described in this guide. The process of running ASDR occurs in the District Administration application; however, there are steps that must be completed in all ASCENDER Student applications.

IMPORTANT: Some of the images and/or examples provided in this document are for informational purposes only and may not completely represent your LEA’s (School System) process.

Prerequisites

Prerequisites:

Before Running ASDR

  1. Complete the end-of-year checklist.
  2. Enter next year information.
  3. Disable Portals.

Run ASDR

  1. Set ASDR options.
  2. Back up database and log files.
  3. Run ASDR.

After Running ASDR

  1. Verify historical and current year data.
  2. Re-enable Portals.

For a complete list of submission rules and edits, access the TSDS Web-Enabled Data Standards (TWEDS) website. In the top-right corner, select the appropriate School Year (20XX), Collection (XXXX), and Submission (XXX) and click Open.

Once on the TWEDS website, in the Overview tab, you can review Collections, Timelines (DUE DATES), and Data Submission Responsibilities. It is highly important to ensure that you review all of these details as they may change according to the School Year.

Additionally, you can use the other tabs on the TWEDS website to review Data Components, Descriptor Tables, References, Rules, Change Logs, and Early Notices.